Time plan

This was the final time plan. It was modified twice during the project.

November 8, 1999
First meeting, start of degree project

December 14, 1999:
Method- and Planning Meeting

March 2000:
(new deadlines)
14: Litterature study finished
14: AFS study finished
21: Requirements capture finished

August 2000:
(new deadlines) Report finished, including
- Arla structure study
- Option list describing and evaluating the alternatives
- Recommendation(s)
- Conclusions

November 6, 2000

Seminar.

November, 2000
Report finished, project completed.

The project was done at 2/3 speed.